Colorado Well Finder › Wells by county › Jefferson County › Applewood
Well records around Applewood show a shallow typical well, but the local spread is wide. The median reported depth is 37 feet, while the middle half runs from 24 to 100 feet. Some wells reach 1,997 feet, so a nearby permit is useful context rather than a guarantee for your lot.
Reported production is generally workable for a home: the median pump yield is 8.0 gallons per minute, with the middle half between 5.0 and 12.0 gallons per minute. This page covers permitted wells within 5 miles of Applewood in Jefferson County and explains what those records mean when you are buying land or planning construction.
Figures are computed from Colorado Division of Water Resources permit records for permitted wells within 5 miles of Applewood. Not every permit reports every field; each statistic uses the wells that report it.
| Depth statistic | Feet |
|---|---|
| 25th percentile | 24 |
| Median | 37 |
| 75th percentile | 100 |
| 90th percentile | 360 |
| Deepest on record | 1,997 |
| Aquifer named on permits | Wells |
|---|---|
| unnamed / fractured-bedrock aquifer | 4,912 |
| Denver | 315 |
| Alluvial | 222 |
| Yield statistic | gpm |
|---|---|
| 25th percentile | 5.0 |
| Median | 8.0 |
| 75th percentile | 12.0 |
| Median depth to water | 19 ft |
| Median water level by decade | Depth to water |
|---|---|
| 1960s | 19 ft |
| 1980s | 85 ft |
| 2010s | 19 ft |
| 2020s | 17 ft |
Applewood’s reported median well depth is 37 feet. Three quarters of the depth records are under 100 feet, while 13% fall between 100 and 300 feet, 8% between 300 and 600 feet, and 5% exceed 600 feet. The deepest recorded well is 1,997 feet.
That range matters when you request a drilling bid. A 37-foot median suggests that many sites may be relatively inexpensive to drill, but it does not support pricing every lot at the median. Local ground is described in the cost model as Denver Basin sedimentary bedrock, and the records also commonly identify unnamed or fractured-bedrock aquifers. Bedrock conditions can change over short distances, so nearby completed wells and a driller’s site review are more useful than a countywide assumption.
The median reported pump yield is 8.0 gallons per minute. The middle half of reported yields is 5.0 to 12.0 gallons per minute, and 66% produce between 5 and 15 gallons per minute. Another 16% report more than 15 gallons per minute.
Low-producing wells are present but not dominant: 17% report 1 to 5 gallons per minute and 2% report under 1 gallon per minute. For a buyer, the key point is that a decent median does not remove site risk. Ask for the well construction report, pump test information, storage-tank size, and any permit conditions. Household demand, irrigation plans, livestock use, and fire-protection expectations may require different planning than a basic domestic well.
The median static water level is 19 feet below the surface, with the middle half from 12 to 90 feet. That is a shallow typical water level, but the spread is substantial. A driller still needs to account for seasonal conditions, local elevation, well construction, and the specific aquifer encountered.
The decade series does not show a simple continuing decline. The median was 19 feet in the 1960s, 85 feet in the 1980s, 19 feet in the 2010s, and 17 feet in the 2020s. Because only 125 wells report a static water level, treat the series as a record of reported measurements rather than a precise groundwater forecast for one property. A current measurement and neighboring well records are better evidence for a purchase decision.
Permit activity extends from the 1950s through the newest permit year, 2025. The busiest period in the records was the 2000s, with 1,129 permits issued, followed by 1,105 in the 1990s. There were 681 permits in the 2010s and 301 in the 2020s.
The most active driller name in these records is Authorized (Pe, Pg), with 1,452 records. Adams Water Well Drilling (Adams, George E) appears on 136, and James Drilling Company (Keaton, Michael K.) on 99. These names describe permit records, not a recommendation or proof that a company is currently available. DWR permit files can also show whether a well was constructed, its reported depth, and its permitted use. Of 6,168 permits in the broader records, 3,538 are recorded as constructed.
The local drilling model uses a typical rate of $50 to $70 per foot for Denver Basin sedimentary bedrock. At the 37-foot median depth, the drilled hole works out to about $1,800 to $2,600. That is only the hole, not the complete water system.
A finished well including the pump, pressure tank, trenching, and electrical is estimated at about $7,800 to $14,600. Your bid can move outside that range if the hole is deeper, access is difficult, casing or grout requirements change, or the site needs longer utility runs. Ask the driller to separate drilling, casing, grout, pump equipment, testing, trenching, electrical work, and permitting so you can compare bids on the same scope.
Records map 317 PFAS sampling or contamination sites, 192 historic mine features, and 131 EPA Superfund or cleanup sites within about 10 miles. Those mapped sites do not prove contamination at a particular parcel, but they justify checking environmental history, nearby land uses, and available water-quality results before closing. Test an existing well for the contaminants relevant to the property.
Low yield and dry-hole risk also deserve a written discussion with the driller, especially where fractured bedrock is involved. Confirm the well’s permitted use before planning irrigation, stock water, or other demands. For a new home, coordinate the well location with the septic system, replacement septic area, driveway, electrical route, grading, and building footprint. A shallow water level can also affect excavation and site drainage planning.
Start with the neighboring wells, especially in West Pleasant View, East Pleasant View, Golden, Fairmount, Wheat Ridge, and Lakewood. Compare reported depths, yields, water levels, construction details, and uses rather than relying on one nearby record. The local data include 3,569 wells with a reported total depth, 357 with a reported pump yield, and 125 with a static water level, so the information is useful but incomplete.
Before buying, make the contract contingent on reviewing the DWR permit, well construction report, pump test or production information, water-quality results, and any augmentation requirements. Colorado exempt household-use wells have a 35-gallon-per-minute pumping limit, and over-appropriated basins may require an augmentation plan for certain uses. For a build, have the driller, septic designer, and excavator coordinate the complete site plan before you commit to a house location.
| Decade permitted | Wells |
|---|---|
| 1950s | 192 |
| 1960s | 228 |
| 1970s | 453 |
| 1980s | 374 |
| 1990s | 1,105 |
| 2000s | 1,129 |
| 2010s | 681 |
| 2020s | 301 |
| Most active drillers on record | Wells |
|---|---|
| Authorized (Pe, Pg) | 1,452 |
| Adams Water Well Drilling (Adams, George E) | 136 |
| James Drilling Company (Keaton, Michael K.) | 99 |
How this is built: the median permitted depth here times the per-foot range for this ground, plus the normal system costs. A lot at the 75th-percentile depth (100 ft) would run roughly $11,000–$19,000. See the full Colorado well cost guide.
Counts come from EPA, USGS and state datasets layered on the Colorado Well Finder map. A count is not a verdict on any one well; it tells you what to test for.
The numbers above are the area average. Your lot is one point on the map. Search the address to see the real depth, yield and aquifer of each permitted well around it.
Map wells near ApplewoodTri-Lakes Contracting is a licensed Colorado contractor serving Applewood and nearby Jefferson County communities with access driveways, site development, new-build septic systems, and custom homes. Early coordination can keep the well, septic, utilities, and building site working together.
Licensed Colorado custom home builder · licensed driveway & excavation contractor · licensed septic installer
A listing photo can't tell you whether a lot is a dream or a money pit. Two parcels near Applewood can carry the same asking price while one needs an $80,000 driveway and a $45,000 engineered septic the other doesn't. The well numbers on this page are the start of that answer. A Tri-Lakes Site Feasibility Report is the rest of it: a licensed general contractor, excavator and septic installer reads the parcel the way we would if we were about to build on it, and puts the real cost in writing before your money is committed.
Spend a little to know. Or gamble a lot to guess. Realtors sell the view and inspectors look at houses that already exist. We're the people who'd build it, so we catch what quietly turns a "great deal" into a budget disaster: bad access, buried rock, steep grade, soil that won't pass for a normal septic, water that's a fortune to reach. And if the lot is good, you've already got a builder ready to do the work, driveway to drywall.
Under contract, comparing parcels, or a realtor with a rural listing whose buyers keep asking "what will it cost to build here?" This is the due-diligence step almost everyone skips, and the one that saves the most.
Driveway, site work, septic or a build near Applewood. Licensed GC, excavator and septic installer.
Got it. Tri-Lakes will get back to you shortly.
Something went wrong sending that. Email kyle@trilakes.co instead.
The median reported well depth near Applewood is 37 feet. The middle half runs from 24 to 100 feet, but the local range is much wider: 13% are 100 to 300 feet, 8% are 300 to 600 feet, and 5% exceed 600 feet. The deepest record is 1,997 feet, so a nearby well is guidance rather than a guarantee.
The median reported pump yield is 8.0 gallons per minute, and the middle half falls between 5.0 and 12.0 gallons per minute. Most reported wells, 66%, produce between 5 and 15 gallons per minute. Low production still occurs: 17% report 1 to 5 gallons per minute and 2% report under 1 gallon per minute.
The drilling model uses $50 to $70 per foot. At the 37-foot median depth, the drilled hole is estimated at about $1,800 to $2,600. A finished system with pump, tank, trenching, and electrical is estimated at $7,800 to $14,600. Deeper drilling, difficult access, casing, grout, and longer utility runs can change the bid.
Safety depends on the individual well and its surroundings, not on the median depth or yield. Within about 10 miles, records map 317 PFAS sampling or contamination sites, 192 historic mine features, and 131 EPA Superfund or cleanup sites. Review environmental history and test an existing or new well for contaminants relevant to the property.
The reported decade medians do not show a steady decline. Static water level was 19 feet in the 1960s, 85 feet in the 1980s, 19 feet in the 2010s, and 17 feet in the 2020s. Only 125 wells report a static water level, so use the series as context. A current measurement and nearby well records are stronger evidence for one lot.
All wells in Jefferson County — county-wide depth, yield and cost figures.
Driveway, septic, site development, feasibility or a custom build near Applewood.
Shopping a lot? Run the $99 instant buildability check →